Assessment 1 Deliverables
Requirements
Architecture
Method Selection and Planning
Risk Assessment and Mitigation
Implementation
Source Code
Source Code
The branch for the source code is main
The gh-pages
branch is for the website content only.
The executable jar file available in the project root (marrrio.jar)
Weekly Gantt Chart Snapshots
These are the weekly snapshots for our Gantt Chart, the more full a bar is, the more complete the task is.
28-01-22
we are now just finishing up the last bit of documentation
21-01-22
14-01-22
After exams week, this is the status of the project, with more work planned to be done in the following week
07-01-22
After a christmas break, this is the state of the project as we begin implementation
17-12-21
We have rescheduled the latter half of architecture (the concrete part) to during implementation as it cannot be done at the moment.
10-12-21
Method Selection & Planning has been given an earlier start date as 4a is now complete, while we are waiting on the completion of 3a to begin work on 3b.
03-12-21
The interview planning & the interview itself has been completed.